T21 & T22 VOIDED SLAB BRIDGES
Construction: Rizzani De Eccher, SPA- Italy, Obrascon Huarte Lain, SA - Spain, TREVI, SPA- Italy, Boodai Construction- Kuwait
Location: Kuwait
Construction Method: Conventional using temporary formwork
Max span: 38.50m
Width: 28.60m
Bridge arrangement: One span prestressed concrete Bridge
Deck section: Voided Slab with 11 prestressed concrete webs and rectangular voids
Height: 1.90m with top slab 25cm and bottom slab 20cm
Foundation: With pot bearings that transfer the loads to Trough Wall
Services: Complete Design check/Bearing check/Construction Supervision
Comments: Construction in 2 stages. Bottom slab and webs first and top slab second.
PROJECT DETAILS
Owner: Kuwait Ministry of Public WorksConstruction: Rizzani De Eccher, SPA- Italy, Obrascon Huarte Lain, SA - Spain, TREVI, SPA- Italy, Boodai Construction- Kuwait
Location: Kuwait
Construction Method: Conventional using temporary formwork
Max span: 38.50m
Width: 28.60m
Bridge arrangement: One span prestressed concrete Bridge
Deck section: Voided Slab with 11 prestressed concrete webs and rectangular voids
Height: 1.90m with top slab 25cm and bottom slab 20cm
Foundation: With pot bearings that transfer the loads to Trough Wall
Services: Complete Design check/Bearing check/Construction Supervision
Comments: Construction in 2 stages. Bottom slab and webs first and top slab second.