Ελληνική έκδοση  English version  facebook  linked in
HOME / PROJECTS / BRIDGES / VOIDED SLAB / T21 & T22 VOIDED SLAB BRIDGES
T21 & T22 VOIDED SLAB BRIDGES
  • voided slab bridges T21 & T22
  • T21 & T22 bridges construction site
  • T21 & T22 voided slab bridges engineering
  • voided slab bridges
  • voided slab bridge construction
  • engineering a voided slab bridges
  • structural model of a voided slab bridge
Close ( Click on the image )

PROJECT DETAILS

Owner: Kuwait Ministry of Public Works
Construction: Rizzani De Eccher, SPA- Italy, Obrascon Huarte Lain, SA - Spain, TREVI, SPA- Italy, Boodai Construction- Kuwait
Location: Kuwait
Construction Method: Conventional using temporary formwork
Max span: 38.50m
Width: 28.60m
Bridge arrangement: One span prestressed concrete Bridge
Deck section: Voided Slab with 11 prestressed concrete webs and rectangular voids
Height: 1.90m with top slab 25cm and bottom slab 20cm
Foundation: With pot bearings that transfer the loads to Trough Wall
Services: Complete Design check/Bearing check/Construction Supervision
Comments: Construction in 2 stages. Bottom slab and webs first and top slab second.