Ελληνική έκδοση  English version  facebook  linked in
HOME / PROJECTS / BRIDGES / SPAN BY SPAN SEGMENTAL / NASSER BRIDGE UNIT 7
NASSER BRIDGE UNIT 7
  • nasser road unit 7 segmental construction
  • constructing Nasser road unit 7 segmentally
  • NASSER_UNIT7_PHOTO5_ALT
  • NASSER_UNIT7_PHOTO6_ALT
Close ( Click on the image )

PROJECT DETAILS

Owner: Kuwait Ministry of Public Works
Construction: Rizzani De Eccher, SPA- Italy, Obrascon Huarte Lain, SA - Spain TREVI, SPA- Italy, Boodai Construction- Kuwait
Location: Kuwait
Construction Method: Segmentally Span By Span using Overhead Lunching Gantry
Max span: 47.00m
Maximum pier height: 12.00m
Bridge arrangement: 6 spans (38.60+47x4+38.60)=265.20m
Deck section: precast segmental box girder 2.65m depth, 15.30m traffic width in left girder and variable in right girder
Pier section: Hammerhead type
Foundation: Deep foundation through piles diameter D=1.20m
Services: Camber Design check/Concrete Stress check/Bearing check/Construction Supervision
Comments: Prestress was a combination of External and Internal Tendons. Tranverse Post Tensioning for the Deck Segments and Piers.