D2 BRIDGE
Close
( Click on the image )
PROJECT DETAILS
Comments:
This bridge belongs to the structural work for the project: "Design of new Highway between Nicosia-Palaixwri stages B & C" Cyprus.
Bridge D2 is located between CH 9+984.17 and CH 10+122.56.
Bridge has total length 140.0m and has divided into 5 spans with equal length 27.60m.
Six precast prestressed beams have been foreseen for each span with total length L=27.80m. The depth of the beam has been designed to D=1.60m.
Transverse beams with thickness 45cm, have been designed in the support location.
Prestress is consisted from 3 cables 12T15 for each beam.
Superstructure connected with the substructure with elastomeric bearings under each precast beam.
Bridge foundation is with piles diameter D=100mm through pile cap system.